Event 1: PPS Board Bond Work Session Apr. 30, 2018

00h 00m 00s
everybody call the meeting to order this is our baby my 17 bond see the goal of working towards a package for the board's consideration at the Madison private rebuild project at may 22nd we can follow not far behind today's agenda we have we're going to go through a number of items during the meeting and the first three items for comment so the items that we're going to go through today is the in comparison summary which is to have two packets here and probably the back yes it's this document so we're gonna walk through that and in your packets you have second of that resolution as a resolution and also at this so this is similar there'll be a resolution pretty Street materials behind next projects it's it will be the resolution so this is what my my Kellogg there was a resolution and there's this for sure if I may twenty seconds or one for Madison ideally also for Lincoln although we were told that it's a little bit it's not track so we have those and that's because they have different aspects and there are different phase their work we wouldn't have an optimization for projects code but we are going to arrive at an authorization of scope for Madison and link out about it there'll be a discussion about medicine we ask as you might recall the last word meaning the ask something to come back with some options and recommendations
00h 05m 00s
and then the last item on the agenda is discussion about cost estimates for pretty estimation work so those are the items yes sorry expect comparison summary so this is the same as the document that was provided last week with exception we can reduce put comment about processes where where they are the project so massively convinced they're all different phases maybe to your comment about making decisions we're trying to make sure that I'm the right information we're gonna have more details on front and others we had a string for what we thought all three strategies together to that trying to the information so so the on this document the Madison option a and option B are the ones that we talked about in detail here last week and then Lincoln ops today we talked about the Lincoln reduced scope option but that is the same data about how this option would compare to the in specs this is the one that we talked about a little more quickly and that's not a recommendation hasn't had a lot of bedding but when the teams got together they look at what are potential cost reductions so some of those things were reduction of reduction of our classroom flex pays some of the partners faces reducing the size of the theater reducing the size of the classrooms and science labs and also to reduce some of the athletic facilities as well moving hitting facilities for baseball and softball the indoor track in the GM covered bike shelters and some other system reductions so those are just things that the team's looked at again not making a recommendation we're just trying to so you're going from there's not the first line you're going three classrooms or the first line a three times 1200 is 5000 quiet then the second column why are you producing by panic yeah there is there's a couple components I don't know also your totals for just before program space done that up because you took out five classrooms are reduced oh and that you're only reducing your total by four I think that that one might be because the flexible flexible pusher right there might be some errors in here these are formula-driven put the lid tricky when you look at the edge spec as sometimes the skirt footages are an average and sometimes they're cool and so the double gets into the details and so what this is is a document that and the bigger the bigger document we looked at last week this is just referencing those cells so there might be consistent
00h 10m 00s
yes and so this maintains this one does not this does not include the team parent center and the help correct yeah so this is something that wasn't put together you know several weeks ago it has not been updated so the updated information our intention is an extra four at home with multiple options questions on this document I know I'm sorry as I go through this more and more and more things do not matter at all it I think this is really bad how to constructively have a conversation about elements how do you ground it in [Music] like this see until you marry well less overall here's the and there have been an ask mm it work if if one of the options is to trim expenditures and that's how we're going to do the reconciliation that each of the projects what would that look like so Madison had won the Lincoln had did not have that go to that same exercise so this is a well they did the first time around before taking the board's attention vote tonight so we still have 136 million dollar shortfall and so part of the exercise to be able to look at what each of the communities what compared to the inspects if there's a number different purposely take and say it's just one of the projects and let the other to be you know fully blown out you could face all three of them it produces the scope of all there's a whole host of different approaches the purpose of this more information so that larger reconciliation that we have information about each of us it's not a [Music] first of all what what is our shortfall actually I would meet arrived there what is the range what are the what are the factors that play into that how much of that is speculative where how its are estimating based on industry is based on last company all about the period out of that incentive what but our truckball is so that's the third item on the agenda today I thought diminished the diminishing of Madison's project and isolation
00h 15m 00s
maybe your what needs to be reconciled but just have any NASA go through me process so regardless of having holidays we go the point here is there could be some scope reduction Oh further further work on that correct yeah we don't I don't just think either of these options these as they are now being wonderful Senate next week they will be updated for example eventually all might not be changing their services that was so I all right how many options we present that because this will have all what our general ideas right now we're gonna work out more tomorrow when we get together the routine restarts or bonuses that we have the option a of the master plan essentially as as they all are and people are familiar with them then we're going to have an option B which is taken into the account but maybe look for what potentially is looking for things that could be modified not exactly sure what those are yet have some ideas and then maybe a third option for each school where there is a phase on the bb-8 a significant piece that could be done at a later phase again that's hard to identify what it is now Lincoln buildings are we talking about tomorrow so ideally we'll have those three options so that doesn't sound like what people are hoping for so I'm wondering that census aboard is no productions is that what you heard and so I I don't want to put you all through a scope reduction exercise if that's not where we're at all would that be helpful and I think yet I don't know what we're at this point would it be helpful to test for consensus kind of intermediate question is are there scope reductions that could be universal like I'd be interested in looking for classroom or to change they have several other things that were universally apply that kind of pursue preemption as opposed to one offs and I think I mean clearly what you said is the reality of the classroom so far [Music] make sure [Music] Gibbons [Music]
00h 20m 00s
so that's what we were the staff to come back with that said it was a discussion about the seismic classroom accessibility within the fashion of distance I've synthesized his face we're talking about access been discussed a while I know the last thing I have not followed up on that if we're not are these you guys about you know Portland they've got that that's it was considered wildly existent relative to what other school districts when stingy and this relative other visitors and I would say but I know that there's you know the the inspects is not managed by osm is managed by a different Department they go through I know they go through a continual process of updating those aspects and they they use information that comes from the projects that could go through design we go through construction as far as the adequacy of those educational standpoint had to occur so the facilities hasn't management all Carbonite room they provide them to us board whatever six years back approved grant input you know they did they were updated that they were largely and I believe the sillies kind of continually made small changes are our aesthetics pretty much they're gonna get customized I mean no but having it as documented yes it's kind of standard practice then the goal of it is to really contour to customize and educational specification to use in the district itself under stay for it to school but so the beaverton educational programs will look very different than Portland Public which will look very different than say an Ashland or abandon or Seattle and so the idea of trying to get down to a very strict interpretation
00h 25m 00s
of a collective approach and to analyze why can be pretty difficult - low threshold it we were talking with the principal's who are teaching whether their staff levels are teaching in there as simple as the idea of what's the utilization rate what we're talking to Peyton and patron others I don't part of it was like well tell me how many square feet and I can start working like classing classroom sizes around what's my available space to teach in or how many teaching stations do we have so there's it's a very dynamic environment of trying to find that balance point of how much space do we have versus how many teaching spaces to be need that starts to equate to what's the right size and is the same numbers for the same you know math or societies for two different teachers are two different pedagogy so the other challenge that we run into is when you start looking at it that square-foot cost when you start trying to equate that into the construction and the design side of the house when we get into new construction that starts to change the dynamic of how the formula works because in new construction for every square foot you reduce let's say you get a dollar for a dollar reduction you can't apply that to a modernization because the the main structure is still there so you still have to build out the space even if we're just gonna do it what we call it vanilla shell and you used to a lot of no finishes but we still have to do things like myself to put fire barriers in place and you still have to create the space so whereas with Lincoln when we start compressing the square footage per classroom if we do that across enough rooms we get to the point where we can eliminate before the building in a Madison however we still have a certain budget exists building we still have to renovate and bring them to code regardless of whether or not we're creating you know a science lab we're teaching in 21st century versus more conventional it so it all becomes this very dynamic you know I need to get 50% of these answers and I can tell you the other half is and but for each school is it starts to get it's different so that's what's one of the challenges our staff is amazing is just trying to develop some level of coming like with our binocular of how to talk about all these schools in different ways replacement school that we make 8 it is very different than an occupy school that we're gonna renovate over multiphase with kids there we start having to add cost for student safety for staff safety for on building temporary services like he some point and a mice project way back in the day staff and students were there you taught me that I'll take care of it we were told we could cut through the fiber-optic backbone no problem it's all back fed the minute we did it top of the school data systems went down so you started having to now add costs in to make sure all that's back fed but that but that's going into your cost per square foot which one you go into these formulas so it's it is a interesting metric to try to nail down how long we have 10 years so I get nervous when I hear that I can just talk problem process real quick our process is we take the inspects and modify that program existing and we were relied heavily on these steering committees which are all internal staff from the different departments including maintenance and operations and security but also from the instruction side so when we need to make changes it's not just the principal and feeling it's not just the project team or making changes it's let's talk about this so the district there's a representative grout the district to say yes this is the right thing to do and when the process as most of that is done for them for the
00h 30m 00s
master plan so the master plan comes to the board so you can see just have made who has had input on that who thinks that's a good idea and then we don't come back to the board approval unless there's no significant changes but that's that's our process and how we try to get that buy-in to the specific site so each other and I appreciate it the last session you're wise I've been hearing there are some features that should be consistent no matter what high school that even from the early schools we've also learned a few things or features that we want to incorporate with a slightly smaller classroom static computer labs perhaps so things like that part forward and so how do we identify efficiencies without and we're building last time these are facility specifications because we're trying to imagine them for teaching learning sort of welcome to the future of which fully articulate and we don't want to end up with and so they have they have to be durable and so so we're trying to get out so that what is that what is that number that we can say this is as efficient as it gets before it starts to infringe on those sort of so once we know what that is that our conversation can shift to sort of yes great summary yeah absolutely in the direction that that we have got to these meetings are helpful because the more variables that we can reduce school is saying we're the participation you can say that's off the table that just makes our life a lot easier and I think we'll have next week is some other potential options that maybe haven't you know like yeah maybe that one's okay maybe that is one that's universal you can start that my position as a well it was a running joke when I was on the grand no pun intended what the rest of the team's practice know is the that's another story that I could just say the Washington High School track needless yeah well I think they're running so they have never that's that's clear is optional yeah I don't mean to say that it should because nobody else got it that's although already expert collaboration
00h 35m 00s
these are footages yeah so this was the ballpark number and it was very much about it's at that specific number but in that ballpark or sorry for feed Nicolas 196 billion and that's 280 thank those at me sorry massenet 184 yes 172 all right offensive numbers are very right now so the option DS are a 30 so all checks a lot more X's on their bottom breaking order around 250,000 square feet well below its Peck range just a lot less footage when you're looking for significant cost savings almost always comes in right obviously once you start programs basis has oh yes they're ready and that's where probably say never classrooms are slightly smaller so how do we get to the very tight program it's still workable from a principals perspective rather it wasn't just a we're just gonna cut to try to keep the numbers down there was a lot of forethought and a lot of cooperation about what does that look like how do we do that not just for the facilities perspective but also how to how are the to the informant function how are they tied together and I'll say just a context to that so these options like the ones I've read up early you're very clear that you know she does not support these it was just they were put towards me I provided input I'm not supporting I'm not recommending what I would look forward you are because it has to offer and I would say what are the key areas hours while we're building a corker what I encouraged
00h 40m 00s
we've done that some a trance [Music] it's it sounds to me if I guess characterizing sure yeah the design document what that is the better the document specification this is what you get a standard cements the standard moon standard sometimes they're just guidelines and sometimes they're we hope to get there so that is the main document that tries to achieve what you're talking about we have a continual process about getting that and one of our staff has got a schedule that's common through section by section this years and it can always get better for sure try to be very intentional in how we do that and make decisions we try to have a lens of full lifecycle not just this project there's opportunity for us to be myopic and say well I'm going to cut cost here because it's better for this project I can even though the long term return very cognizant of that and not do that members now are standing steering committees cherry - whose team heads out all that up and so we're starting to change the conversations are evolving now so we are talking about context versus effects that was our first in capital expenditures versus where our long-term operational costs and what does that mean we can go with a very inexpensive system right now we're gonna be changing the filters four times as often the filters are hard to come back for these one-off systems so that translates into no hundreds of thousands of dollars every year and by the way the life expectancy of those units use an air handler you could you may reduce the life expectancy by ten years and so instead of a 30-year unit we now have to put into the capital renewal program at the 20-year mark a two hundred three hundred thousand dollar air inter replacements and so we're trying to find that balance but not just in a silo but reaching out and working with with bam about what what makes the most sense what's that right balance point so we're trying to overflying on our own correct we were trying to overlay all of that and so yeah being is that as we overlay all these different criteria we start to get down to that okay of 20 let's say possible options now we're down to two or three okay now we clearly dive in about it's going to help us get toward LEED certification levels it said the right equilibrium point as far as first in cost versus operational cost and light turn I like I stopped then we get into really the preposition at that point at what the system makes the most sense for those about the meeting but as far as the overall project yeah absolutely yes is if your sometimes you'll get into strict limitations as far as the structural elements and we going with our brand lair handler maybe high-efficiency but it weighs more well then we'll have to reinforce the structural systems which if it's among group or house that has to embrace different types of systems with if it's a hydraulic system that Ronix have a lot of using water so now we have to allow for the weight of the water in the pipes well you know sometimes you start running miles of piping that starts to add up and so to be to do you do with just a you know terminal units on the groups that have were just moving air it all interplays but actually the reasons that the project managers for a Lincoln that's not here today is there's a meeting happening right now between our mechanical jobs the project needs and the engineers
00h 45m 00s
okay pressure this sure yeah I'll hit this fairly quickly have also in your packets this document that support of education media materials cover sheet and item B is Kellogg master plan the documents that are the ones that are in grey I didn't provide the self stuff that went in December it's just civil attachment yeah I'd love to say that we're super consistent with all of this but certainly you know the big details we are that's all kind of touch on and then the project teams operate same substance so all just a little dude walking through the staff report real quick and kind of touch on a couple highlights the PowerPoint presentation and the staff score really get a few ones they'll talk about the process for example in the Madison I talked about the number of internal groups and meetings that we had over 20 meetings yeah just to kind of give you an idea also we talked a bit about the public engagement process standing at the designed advisory through having additional public meetings for example having seven design advisory clear meetings one design workshop one open house and then we'll talk about the schedule as well because when this comes forward we want to have a plan a schedule budget for Madison so we have the contractor under contract you know that is new visit last week and then we'll call this conversation those are elements of the real area so hopefully you know the idea being in it see how high that's really mean like the most important thing this is the screen very good that's in my mind Scooby framework and sort of really still developing right as that effort was going on and this was being designed there would be
00h 50m 00s
do things learn that were applied to the plan and then instantly were up dr. Valentino on the spot I will all sort of which is just do we feel like there's been insufficient engagement from your team working on the middle school framework our hold all of our hopes and visions for six to eight education and what birds need air that will guide I think more recently there's been more but I think those whole framework was truly develop in isolation to work and so I don't think that there was a lot of accounting before what the possibilities were antidote and this began last and the way it came together enough or inclusive enough just to suggest that the middle school framework actually responsive I think we need stepped in and and also because from full engagement and everything from well weren't invited to people being invited and counseling to for whatever reason that didn't seem to be a reason to be a part of these conversations change but only because we talked about the relationship between program not being the constructional project the instructional program of vice versa so that's taken some conversation including the CTE master plan redesign really that's an example that bracelet what what are the conversations that have had and though they need to be had that will allow for a better integration instructional program in the construction projects I don't I'm sure was there sufficient internal expertise gotcha climatic so haven't found any flaws per se programmatically we're still tight we're still trying to make it schedule is perfect so where are we in terms of the Kellogg design the last several months preserve what was there a $50 off I'm not talking us are there ways to inject anymore and maybe maybe I think our county is just getting up to speed on some of the Kellogg's the master plan he was going forward a lot of the input senior director and Brenda box biotechnology invited out to the steering committees and I think through 10 different already so give enough to speak there but we plan on coming back to the Lord well Kellogg's still going
00h 55m 00s
tell me that secret in my god I want to double check with the next so everybody just this will be what we but sounds like to maybe ten more attachments direction of decisions by resolution fairly straightforward we don't look at a range of options kind of sweet straw poorer we light on and that's [Music] the off cycle fine that's my guess all those cartridges that's a great question from the instructions on to proceed going forward but there have been some reduction there's concern but I first concerned about the overall capacity and what that's the thing I think history nights is 675 another but we're going to be a rhythm time at some point learning spaces ESL fashion there for instance what I don't know it's six of our trailers so I'm pointing those out it's tied to this question right company [Music] [Music] all of that was going through my head I'm like peddler expire we have a designated Marcel classroom so you know it's these kinds of questions around how do we are there other we're gonna building me the middle school this should be sort of the demonstration site for what we mean by should have everything we want for all of our students yeah so to open something less than that right so I just want to make sure there's enough there that we can work with and populate programmatically that you can't point to it Google whirring for across all of their process
01h 00m 00s
education side of EPs to come back with the answer the answer the question is if I rebuild it because school so what you're looking at is the original what we're what we're now talking about is less than this okay so yeah it's probably theory that we're not the only ones doing this you know so so let's have a conversation about what other aspects look like what are you know 21st century no fools what does let's look at the new school beavers in this bill not saying that all that didn't go into the belt that he had spent but if we're kind of celebrating have the new flat specs come to the I know patella before they were still around form and so we used the draft at that time I don't know yeah and you want to say within three years here that the cops are putting up with middle school it takes a ton of dollars so we got a 50 million dollar that's nice yes at what was the cost of that is that worse so there are examples I mean I would want a little time to answer this question for a small team of us to go through that draft for school specs see if anything proposed in there would be a roadblock or to do with that school and then kind of look at what other districts have done just to make sure we didn't miss something that could be built in or adapted it just in the way I'm asking search our crews on you start to imagine this transition of six period and that does they're different efficiency that gets built in sure yeah I'm happy to getting that set up okay that's a that's a good question and I have to defer to people who manage the smaller but also it is found that in construction it's the thought that that is an agenda item for the amount of conversation it's a great question so when we did the
01h 05m 00s
amazing process last summer we showed it to the both Madison our goal is two years especially Madison we really don't have something else so that's the goal but that's a pretty tight hole and similar with Lincoln but then again Lincoln doesn't have the same constraints you can start really massives really the driver and we really want to do it two years ago Kellogg is so we're expecting that building to be done early January February two weeks ago the estimates for and [Music] sighs was the same project that was a risk Oh - correct so the question then is how did we get from of X number two yes so I'll talk through all the documents there's a lot of detail here so please feel free to interrupt with questions of everything literally but I'm going to give it a try this this star here is really but you also have document call upon budget variables so I thought it'd do quickly this kind of watch just walk to that real quick I talked about what the variables are that go into making up these college budgets and then you can talk about what ranges or variables what's reasonable there so when we start putting together bond budgets there's really some primary variables are just at the animal part costing the big one what's the cost of construction there's different ways that you can estimate that but 2012 on we took the square footage size that was meant by the bullring facility plan kinds of dollars per square foot industry norms and here's what the range is we're just right down the middle and that gave us our car customer the 2012 on had a nice one-page sheet that said here's how to do hard cost and all these other variables so take out your pencils so the hard cost is is the biggest number for the 2017 there was people all the schools high schools master planning effort buildings effort right or level all those international cost estimating firm they were contracted directed with PBS and they provided the hard costumes sob costs are the cost that are intrinsic to the building architects are the biggest architects engineers insurance that we have to purchase for the project maybe a little bit under
01h 10m 00s
the next one is fixtures furniture and equipment that's the facility just chairs correct correct and then contingency pick up the phone call about anyone in the construction let's say was a project contingency for new construction we're gonna be 10% contingency your renovation I'm sure places that's the norm you'll hear that all the time and then swing space dead space that's a bi project Benson of course it's funny face from the how students you know in temporary spaces that mrs. Lincoln to do something and then on the back escalation here one fairly familiar with that what we're hearing in the market there's no one this is what the explanation number is but we really care about four to six percent people are estimating I made a note in here writer level all puts out an annual quarterly report and they do it by area juices nice down and so they said that I experienced about 6% and the likes of all pollinators in January we do so that's here on seven or eight percent I know it just for a year anyway yes I'll get into that I think like I think Lancer that minute so what I put down here is a down so I have a spore Mila how do you get to the project number it's the hard cost plus these other variables and typical I'd say industry ranges is what everything down here and if you pick up the phone and call we actually run less than that we have been running less than that but so I put fifteen to thirty but he'll hear 30% of Clackamas use 35% so how much of that was walking through sandy high school and after that today lowball budget issues and later I think some of the other recent projects there were some decisions that were probably made in a box hey I prefer to the steering wheel on for lying on that we didn't have that in fact that the partners really were more independent if you will and then information where they fit we've been trying to focus so when we make decisions about value engineering you know there's some representing the entire district but our FF&E budgets that we have in here are built on nobody we are calm and are designed we are going through or continue to go through process or we have tried in consulting and help us go through our standards so the formula you can see here is pretty straightforward I put some ranges on when I think our industry standard greens we can certainly have a conversation about that I'd be very surprised there was a lot of argument so that segues over to the big 12 font also had was a board reserved 20 million dollars in addition to the program decisions there was a two-horse survey in 2012 escalation of the program levels of the projects didn't have a built-in unlike
01h 15m 00s
so this document what I did here I just I produced this or really this exercise and this is Mike on the best attempt to answer the question of how did we go and certainly have some discussion about this quite a few people have never seen this and I've seen this detail I haven't there is some subjectivity in what I did under the first category kind of hard to read or understand it was a bomb development June 2016 from January 2017 there's three colors of columns kind of lines I'm not sure if they are but I believe they're all different colors the first one says pre bond budget estimate conservative the second one says pre bond budget estimate below the road and the third one says keep on budget estimate and progressive what I did I just took these variables these range can we just talk about and on the conservative side you said I wouldn't go to the high end of all and the middle of we go to the middle and on the rest of them we go with a low and so we can see where those budget numbers come out all walk through the Madison one group ask questions so the Madison they'll walk through each variable hard cost I put a note here that says our LDS tenant that means to came from reliable they're the ones who gave us down hard on sester the soft cost I put a 25% I mentioned earlier that 30% some pretty common part of soft cost is administrative project management program management we actually carry that outside the project so we run about 5% - 25 % here the FF&E is 16 dollars a square foot contingency at 15% renovation work no swing costs from Madison although the problem will be some and an escalation 6% of four years and as your eyes move across the page from the different estimates I tried to highlight where the changes are so from the pre bond the conservative one to the middle of the road all I change was the stock cost the escalation and then put a pre bond budget aggressive again I just changed the soft and you can see on the polls how those changes impact the next column over on referral February 2017 is the information I have as far as what went into the actual bond budget numbers that paid up the portal I don't really but I don't have detail of that I can't answer all questions about how decision-making was that this is the information I have how we got there so for example Madison the hard cost number wasn't the right level number a little lower number I believe the intent that that time was that there could be some cost savings there was I believe there was a I was involved in this if there was some bullet points I hate here's here's where we might be able to save some money so we had somebody well that was information I was I don't know if this detail was presented the number yeah it was basically represented that member tsoumas a crew madison's 146 [Music] in a four pager or something from that it's basically said you could fill this so it was presented that this was the project they were going to get and many clients and his future sure there was no discussion about like we don't know if
01h 20m 00s
we can make it it was here here's here's the school that we wanna build and here's the cost the only thing that was in play frankly between the two options of the Kentucky sag was whether Kellogg was going to be in the package it wasn't well I don't I mean relative how we BIR bigger estimates cuz we didn't have those tire of a dress this was given to us as like this is how much it costs to build there are children chatter Lord it's like you can build the school for a hundred so there are representatives that are I don't know and that's like I think some of this makes it look like it's very linear how this has come together with the deep range it was just well he even got a bottom line you see that I don't think any of this detail is so might not wasn't right I'd say some of this is to say that nothing was presented like this so I created this to say here's how I can best explain I've created those two based on our cost from the cost estimate our in deducing fees which is very similar to what we did in 2000 so you were hired for the due diligence process and so they provided just car custody so they were really master planning process I don't recall there were in the Lincoln because that was part of the consideration around [Music] dollars so to Amy's point for example and the B side there's the Lincoln High School in high school it has the construction cost budget cost for both for replacements [Music] so the renovation policeman was 186 but no worry that doesn't say the projection of the outside estimators well and something bad like that terminology that's but that's definitely using that terminology based upon the logic that chapter one here the details are something else what but it's certainly this information in this master plan the last two clubs
01h 25m 00s
the master plan budget initial is when so faster process fallen past and that's when stretch comes to SM okay now go in action so all of the teams then so the next step is looking execute to work we need an approved master plan that goes to the board that master plan needs to have a plan that schedule budget those teams all went out and got updated cost and then brought it back holistically not just a hard cause bring back everything and so that's what the very first estimates or those came back in from the Cost Estimator brothers for different cost estimators on projects there are cost numbers plus what we believe are realistic soft cost numbers of members and so that's what that master plan budget initial column X and then the master plan Budget Reconciliation slash reduce scope as what we've tried to do to get back into line to reconcile but that has included reducing scope and it's also definitely included efficiencies to learn things and corporate those the range of the house looks like it way back up to about what is and that's like about it so this this chart here for bars of the four different schools and this line is the total of those four schools so it's not the total you'll see simply remainder anywhere that's just the pipes of the 580 that you see I'm here is the total I know there's a lot of de down here but there's a totals for modernization projects budget 580 number and then I show the other stuff that makes up in the Senate I mean I'm just looking at this I don't have [Music] the numbers we're allegedly trying to work with now there to get to the numbers that we have now with certain remarks okay so if we're going to build buildings that are even remotely related even using the current expense with all of their shortcomings whatever they may be do that okay so so we cannot do what we said we say now we're gonna do three high schools and help 180 makes a punitive okay so we're not you're the money that we've got we were very clear that's a great question so the exercises were to get down all the projects stay within budget and complete all the projects it'll trash stick be different than the master plan I don't know
01h 30m 00s
which is still under construction what they do know is we non-negotiables that we've said how they out of you we can't we can't certainly not now so we're going to come up with either conversation is your bond counsel and because Benson has specifically mentioned so the language has actually brought it up and there was some very specific things called out which you have to do so it's broad enough to cover things not mentioned but there was enough there were specifics that you had to hit and look at the language last one but it says renovate replace schools something something including Benson come on so you can't just a further Benson to the next one but you also don't need to be here to begin work a lot Benson which is actually more in line but our ability to create the vision purpose and that we you want to see the disturbance by hey we did you do some things to this how much well there's no LaVon language we we just need to make some renovations to fences but I mean I think what we want to do is we want to align it with the process that will enable us to figure out what exactly we want me out of that facility and what is our first priority or what can we sort of discreetly pull out of that work to begin the first phase or in the enrollment consideration or I mean it's all very difficult because we're needing to make these decisions before we have that quality low vision of what that 21st century see at this point that's the least governor's very least of them it's the biggest problem is that was not doable from the day it was referred to the voters this was not doable I don't know how we came up with it I don't know who that number is at this Inn actually I would like to hear from I don't think you guys Jessie you weren't around an era guy hope you don't mind if I put you on the spot you speak a little bit to the process of how the district arrived at the budget numbers in the master planning process that went into the bond package relative to the original estimate that fair for me to ask you to speak it out sure to answer for my part of the process was so I managed to master planning that created a half of the project for me these costly sparse we came up with a construction cart cost estimate which is just like hospital so
01h 35m 00s
so I can tell you that I know what that cost me buildings try to figure out well I know that as they taking the hard cost even from guest leaders and we get into what we call parametric cost modeling right yeah yeah you have a hard number start up find that this this very empirical process by which you start to generate all the additional numbers again that all that always rolled up you know and hand it over to the district as far as what are what are those numbers no there's usually a balancing act that has to go along with any of what's the mill rate gonna be there's there's a lot of conversation that happens at that point behind them you know in a closed session about where does the cross come in it cost what is the cost modeling end up at versus what can this voters really support and there's going to be a lot of science that goes into taxation rates and that going to stop the hyper-technical that's their specialty about this is what the voters can consider in our debt service and that kind of stuff now how those decisions are made there's a balancing act typically I can tell you only what you would do is you would go in and say if this is the need to deliver those specified program at that cost versus what we what the voters can support you then start supervising you a line but keep talking about you Alliance scope schedule budget to say okay if this is where the plan is going into this process before we refer it okay we need to drop the ask and we have to align the scope with the budgets you start backing into it if the voters can support a 790 million dollar bond program then that's going to translate into a Kellogg Madison Lincoln 150 million of Health and Safety and and with the bad advancement was heavily involved with that so overwhelmingly help the safety anywhere from 77% ask out but water paint asbestos you know killer killer arguments with a public art that choice of words but persuasive that's why people were going to vote for the bond then you get to the other people other projects and modernize Madison traditions renovations and rebuilds you're down to 36 percent versus the other ones where they say between 63 and 77 percent and then you go to Kellogg that way just an imam Kellogg's at 43% on the voters the lowest priority except the very important caveat that the most effective way for us to mob just answer your dicks now that's at three schools versus touching and then the other question I'm just let's get cramped down so the vast majority of voters support both that's empty did you know a dog on the 800 gr on the ladder would be a tough sell so you know clearly in 850 would have probably allowed for more flex and still as number so enough hit but if I go to their birthday 50 so somehow the decision-making had that been went down too 750 or 790 to keep all the projects in so ideas what
01h 40m 00s
was politically palatable is finding the aspiration was for schools how the problem is sort of not scaled down and so and I've only been airing bad you know fantastic high schools there's no point building something that's that's so how are we going to true up sort of thinking those dreams come true perhaps it at all for me even if it was conservative middle-of-the-road or aggressive it was never anywhere in the ballpark of what was voted on bond package like the final consideration of the bond stakeholder advisory committee direction to include Kellogg and to bump up the bond the total bond request but it wasn't commensurate like Kellogg's estimate was forty five million or something and the additional amount of the request was a forty five million but it was that the rest of the master plan budgets came in to override it as a recommendation to the bond stakeholder advisory was state Advisory Committee nobody ever said these high school numbers are right these were presented as like if you these are in the package and there was never any suggestion of by anybody of like taking them out or pouring them the numbers that weren't presented to that citizen committee per the were fake numbers I think they weren't here's the project but they they clearly both the numbers to get into the project even were part of that I mean is that that because if that's true that that's the numbers that were given to the board - so is there yeah and speaking to Ken Fisher who's here so Ken and I both provided it on how one might go about this kind of work as far as the decision-making and how these actual project numbers you know like I think those numbers are many another bottom line numbers right I had information that kind of gets me to the other stuff but I don't know the decision on the ground work sites in to step three and I doesn't write about what the cost will be I'm sorry saying tonight your understanding of whatever yes this level of information and we have to we have to take some action personally I think the next spin around and okay but longer term I think there was something desperately and fundamentally wrong with the way the process that led to the garnet package and I think a thorough analysis of what the hell happened and make sure that it never happens again this is putting in jeopardy the long-range plan for pts renovation for the next 50 years of these we are going to have to we are going to have to be so squeaky clean going I mean we are going to deliver the best buildings we possibly can given the money that we have you're going to have to restore faith because we have just violated and they have no relationship to the reality
01h 45m 00s
of the numbers that were presented to whoever develop the bond package it would share it together this is what you can build these three high schools or two to the governance level which was the bond committee and the board and so there was never any conversation at that time and perhaps there should have been you know it she's been tagging in that way that we had more conversation about how do we know that we can build these or what you're saying I think the one element were in all these questions where I think the real cornerstone of a lot of this conversation occurs is is how is that translation from what was brought forward by by staff whooa Sam to what was referred to as there's you know that's one things where you may need get those who were heading above us and at the time aren't at the table today because they're gonna have part of the history that we don't have today okay so which would be Jerry I mean he had some of that is stuff where I just don't have that he had a story I can track all the way through what has been was referred upward from you know through staff and what they've done but they're just members not sitting at the table who might have some of your I think this is a very important conversation to have and we continue the process on concurrent streams so Polly I'm gonna give you the last word oh yeah but actually I'm gonna throw it to you okay at the moment I don't give a damn about the numbers I don't give a damn about the money which takes a lot because I go back freida to questions you asked earlier and then Julie questions you were asking that I don't think have been answered adequately at all and I think especially in light of those what you said earlier isn't true I don't think that we necessary we have to make a decision right now we may very well not have that critical information we need are able to do that we may just have to blow medicines deadline a little pain will ease you on all three of you do you think we need to revise the inspects before we do leave have a carpet do Dean have a decent set of parameters for Kellogg and for our high schools or do we need to say to help with the money if all of the schedule the hell with the deadlines you got to start over I really and I promise you whatever your answer is I'll be behind you with a big club oh yeah yeah growing new administration small but like we were tasked with understanding the history institutional mechanics for how we arrived at this point we're committed to doing some forensics around that Oh regardless of how we got here we know there's a significant gap and I haven't we need to think about sort of how we're going to convey that understand
01h 50m 00s
today the broader public so that we're delivering on what they're expecting and I appreciate that the team is continuing to go back to identify some efficiencies we'll certainly take a little fighter to come look at are the specs spaces we can live with for the kind of pedagogical direction we want to go I think I'm on the same page with the board and not wanting to sacrifice whatsoever any parity in the facilities that we build but I think we are gonna arrive at a resource gap and so we should be having the conversation as we continue to get get complete information around our and a bridge that is it a phasing of whatever order of schools you have a more immediate schedule here a log which is an important comprehensive for many reasons we should try not to delay we have a little more time to dive in a little deeper on the others around what is the order I think he's good phased is there a way to bathe them I don't know but there's also lots of good work that continues to to occur with the resources we've been entrusted with and so being good stewards we should be highlighting those things because work is happening every day right now especially in the health and wellness which is what polled by what people expected to see and there's been no interruption there we should sort of ensure the public beatles continued confidence that we have a team is going to deliver on this bond work i don't believe it's a management or it's just simply trying to deliver on something well constraining resources at this point but I was trying to understand is even the count over forty six percent escalation annually it still doesn't account for the original passing of the bond and there so Benson should be as fabulous as think it should be as fabulous as Madison should be SPECT was this prank that or any other school so how do we make sure I can find the quickest way to get there in the most personal resource responsible Canada I think we all understand that's kind of the question right now an immediate step is to continue having this conversation has been informative these work sessions that work out of all of us expectation is that the calibration between education options so so you just extrapolated second zero tolerance right like this wasn't information that estimate which was they came from the outside auditors know so the habían blow those numbers of the stains is based off of those best practices 6% 5% representative it's the
01h 55m 00s
parametric cost one with regression that generates but I don't think it went no we didn't know I assume that all of the building since Benson chemically knows the leaves that there were I I don't recall them he ever saw what those were but we knew that he's theoretically existed now you're having two rivers in every right so what I would suggest in port numbers